Power Company to Spend $93M to Resolve Clean Air Act Violations

Duke Energy, one of the largest electric power companies in the nation, will spend approximately $85 million to significantly reduce harmful air pollution at an Indiana power plant and pay a $1.75 million civil penalty, under a settlement to resolve violations of federal clean air laws, the Justice Department and the U.S. Environmental Protection Agency announced Tuesday. The settlement also requires Duke to spend $6.25 million on environmental mitigation projects.

The agreement, filed in federal court in Indianapolis, resolves violations of the Clean Air Act's new source review requirements found at the company's Gallagher coal-fired power plant in New Albany, Ind., located directly across the Ohio River from Louisville, Ky.

The settlement is expected to reduce sulfur dioxide emissions at the Gallagher plant by almost 35,000 tons per year, an 86 percent reduction when compared to 2008 emissions. According to DOJ, this is equivalent to the emissions from 500,000 heavy-duty semi trucks, which is more than all the trucks registered in Indiana, Illinois, Kentucky, and Ohio combined.

The settlement also requires that Duke spend $6.25 million on environmental mitigation projects, including $250,000 for the U.S. Forest Service to address acid rain in downwind national forests, $5 million for one or more other projects such as conversion to hydro generation or hybrid vehicle fleets, and $1 million for environmental mitigation projects that will be allocated among the states that joined the settlement.

The states of New York, New Jersey, and Connecticut, as well as the Hoosier Environmental Council and the Ohio Environmental Council, joined the federal government in the settlement.

"This important settlement resolves lengthy litigation on very favorable terms," said Ignacia S. Moreno, assistant attorney general for DOJ's Environment and Natural Resources Division. "The settlement will achieve substantial emission reductions through the use of natural gas and other control measures, and it includes important steps to mitigate the negative impact from past illegal emissions as well as a significant civil penalty. The Justice Department will continue to vigorously enforce the Clean Air Act to ensure that the electric utility industry complies with laws designed to protect human health and the environment."

Cynthia Giles, assistant administrator for EPA's Office of Enforcement and Compliance Assurance, said, "Coal-fired power plants are big contributors to air pollution, which is why we need to make sure they comply with the law. As a result of this enforcement action, Duke will make large cuts in air pollution, which means cleaner air and better health for the millions of people living in communities downwind of this plant."

As a result of a lawsuit filed in 1999, Duke went to trial in May 2009 for the alleged violations. At that time, an Indianapolis jury found that Duke violated the Clean Air Act by failing to obtain required permits and pollution controls before making modifications to Gallagher Units 1 and 3 that caused significant increases in sulfur dioxide, a chemical compound that can cause severe harm to human health and the environment. The trial to determine the appropriate remedy for these violations resolved by the settlement had been scheduled to begin on Jan. 25, 2010.

The settlement requires Duke to either repower units 1 and 3 at the Gallagher plant with natural gas or shut them down to remove all sulfur dioxide pollution. This natural gas repowering will also reduce other air pollutants, including nitrogen oxides, particulate matter, mercury, and carbon dioxide, DOJ said. The combined nitrogen oxide emissions from units 1 and 3 are expected to decrease by about 2,198 tons per year as compared to 2008 emissions. By using natural gas rather than coal, Duke will eliminate emissions of particulate matter and mercury from the units. EPA also expects a 50 percent reduction per unit of energy in these units’ carbon dioxide emissions because of the switch to natural gas.

The settlement further requires that Duke install new pollution controls for sulfur dioxide at the other two units at the plant, units 2 and 4. The work and projects that are required by the settlement will, when fully implemented, result in substantial improvements to the air quality for the communities that are the most heavily impacted by the Gallagher plant's emissions, DOJ said.

This is the 17th settlement secured by the federal government as part of a national enforcement initiative to control harmful emissions from coal-fired power plants under the Clean Air Act's new source review requirements. According to DOJ, the total combined sulfur dioxide and nitrogen oxides emission reductions secured from these settlements will exceed nearly 2 million tons each year once all the required pollution controls have been installed and implemented.

The settlement does not resolve other pending litigation against Duke for violations of the Clean Air Act, including an appeal to the U.S. Court of Appeals for the Seventh Circuit involving the Wabash River Plant located in West Terre Haute, Ind., and an enforcement action pending in the U.S. District Court for the Middle District of North Carolina involving the company’s coal-fired power plants located in North and South Carolina.

Duke Energy, which is based in Charlotte, N.C., supplies and delivers energy to approximately 4 million customers in the Midwest and the Carolinas. The proposed settlement was lodged Tuesday in the U.S. District Court for the Southern District of Indiana and is subject to a 30-day public comment period. A copy of the consent decree will be available on the DOJ Web site at www.justice.gov/enrd/Consent_Decrees.html.

Product Showcase

  • SlateSafety BAND V2

    SlateSafety BAND V2

    SlateSafety's BAND V2 is the most rugged, easy-to-use connected safety wearable to help keep your workforce safe and help prevent heat stress. Worn on the upper arm, this smart PPE device works in tandem with the SlateSafety V2 system and the optional BEACON V2 environmental monitor. It includes comprehensive, enterprise-grade software that provides configurable alert thresholds, real-time alerts, data, and insights into your safety program's performance all while ensuring your data is secure and protected. Try it free for 30 days. 3